On June 2nd, 2022, ECEC signed the SNG gasification process package contract for the methanol integrated utilization project (Phase IV) of Anhui Tanxin.
The Phase IV of the methanol integrated utilization project was located in Huaibei, Anhui province and ECEC’s EPC scope covered coal gasification, purification, air separation and utilities & facilities for 600kt/a ethanol project.
For reference, the 500kt/a methanol project of Tanxin Phase III EPC contracted by ECEC adopted SNG gasification technology and commissioned successfully on April 28th, 2022, in which the coal feeding capacity of single gasifier reached 2000t/d.